Small Modular Reactors Gain Permits as AI Grid Crunch Deepens
A year of permits, but not yet of power
In 2026, small modular reactors stopped being only paper designs and became physical projects. Several have regulatory approval, and some now have concrete in the ground. None of them is yet supplying electricity to an AI data center. The gap between those two facts is the story of the year. The tech companies that have signed for gigawatts of future nuclear capacity are running into a grid that is already falling behind demand.
The regulatory record is real. The Nuclear Regulatory Commission voted on March 4, 2026, to issue a construction permit for TerraPower's 345 MWe Natrium plant in Kemmerer, Wyoming. The Department of Energy expects that project to be finished in 2030.2 On September 29, the NRC approved the first U.S. construction permit for GE Vernova Hitachi's 300 MWe BWRX-300 at the Tennessee Valley Authority's Clinch River site. The review reportedly took 14 months, four months faster than planned.2 The NRC called it the first commercial small modular reactor to receive a construction permit. Recent reforms tied to executive orders and the ADVANCE Act set 18-month deadlines for these reviews.7
Other projects moved too. TerraPower began nuclear construction at Kemmerer in April 2026. Kairos Power broke ground the same month on its 50 MWe Hermes 2 plant in Oak Ridge, Tennessee.4 Hermes 2 is designed to send up to 50 MW into TVA's grid, which serves Google's data centers in Tennessee and Alabama.5 In Canada, Ontario Power Generation is building its Darlington BWRX-300 under a 2025 construction licence and applied for an operating licence in March 2026.3
The demand signal behind the rush
The customer list explains why SMRs moved from specialist nuclear outlets into mainstream tech coverage. Trackers count roughly 9.8 GW of advanced nuclear capacity under contract with AI and data center buyers. That figure includes both new SMR deals and contracts with existing plants.322
The largest deals:
- Meta and TerraPower: up to eight Natrium plants, worth up to 2.8 GW of baseload power and up to 4 GW with storage. TerraPower says the first units could arrive as early as 2032.2
- Meta and Oklo: a prepayment for a planned 1.2 GW campus in Pike County, Ohio.2 Combined with its Vistra contracts, Meta's nuclear agreements cover up to 6.6 GW of existing and proposed capacity by 2035.5
- Amazon and X-energy: X-energy's own prospectus treats the 5 GW headline as a target that assumes Amazon exercises every option. The company has not reached a final investment decision on any reactor.2
- Google and Kairos: a 500 MW fleet.4
The reason for this buying is the load forecasts, and they are large even where they disagree. The International Energy Agency projects global data center consumption of about 945 TWh by 2030, within a wide range of outcomes.29 NERC's January long-term assessment projects U.S. summer peak demand rising 224 GW over a decade, 69% above its earlier forecast. It flags MISO, PJM and ERCOT as at-risk regions.25 McKinsey expects data center electricity demand to grow 24% a year through 2030, with power supply trailing compute demand until then.28 TrendForce estimates that grid capacity kept up with data center demand through 2025. It expects the two to start diverging this year, with the gap widening sharply from 2028.27
The forecasts differ mainly in what they measure. Some count announced projects, others count electricity actually consumed, which is why U.S. estimates for 2030 range from a few hundred terawatt-hours to nearly 800.2930 They agree on the direction of the trend. They disagree on how steep it is.
The grid is already the bottleneck
The near-term problem is grid hardware and connections, not reactors. Sightline Climate counted about 16 GW of U.S. data center capacity slated for 2026, with only about 5 GW actually under construction. It expects 30% to 50% of this year's openings to slip or be cancelled.2226 The named constraints are transformers, switchgear and battery systems. Lead times for critical electrical gear have stretched from 24 to 30 months before 2020 to as long as five years.26 Grid connection waits in Northern Virginia, Phoenix and Dallas run four to seven years.26
Ratepayers are starting to pay for this. In PJM, the grid region serving 65 million people, the capacity auction price rose from $28.92 per MW-day for 2024/25 to the $333.44 cap for 2027/28. The market monitor attributed 63% of the 2025/26 increase to data centers.22 Gallup found in May that 71% of Americans oppose a local AI data center.22 Nuclear Newswire has also covered a voluntary Ratepayer Protection Pledge, signed in March by seven tech companies and hyperscalers, as data center growth turns into a political issue.20
The pitch for SMRs is that a reactor next to a campus lets an operator skip the interconnection queue entirely.13 The 2026 pipeline shows how little of that is happening so far. More than half of this year's U.S. projects plan to connect to the grid, and only about 3% are designed to run on onsite power alone.26 Hybrid setups make up the rest, and they still rely on the utility. Dedicated-reactor campuses barely appear in current construction.
The skeptics' arithmetic
The strongest criticism comes from the Bulletin of the Atomic Scientists, which argues that nuclear power cannot meet data center demand in the next several years, when AI load is expected to grow fastest.12 Its central point is scale. A 300 MWe reactor running nonstop produces about 2.6 TWh a year. U.S. data centers used an estimated 312.6 TWh in 2025.12 The Bulletin also notes that tech companies' largest announced nuclear investment, $650 million, would not pay for a single Natrium reactor. One estimate puts that plant at $9.4 billion.12
Some of the Bulletin's details have aged. It says no SMR project is under construction in the U.S., but other trackers report that nuclear construction at Kemmerer started in April 2026 and that Hermes 2 broke ground that month.124 Its argument about scale and cost still holds. First-of-a-kind SMR projects reportedly cost $8,500 to $10,500 per kilowatt. The industry's target of $4,000 to $7,000 depends on building many identical units, and critics say that could take dozens of repeat builds.3
Fuel is another constraint. Several leading designs, including Natrium, Xe-100, Hermes 2 and Oklo's Aurora, use high-assay low-enriched uranium (HALEU).1 Centrus, the only U.S. producer, had delivered about 900 kg of HALEU by mid-2026. TerraPower says its first core alone needs about 15 tonnes.4 Centrus signed a $900 million DOE contract in June to scale up enrichment, but that capacity will take years to build.4
Microreactors: real fission, little data center load
The most striking technical results came from microreactors. An executive order directed DOE to bring at least three advanced test reactors to criticality by July 4, 2026. Four made it under DOE authorization, outside the NRC's commercial licensing process: Antares, Valar Atomics, Deployable Energy and Aalo Atomics.4 One tracker reports Valar's Ward 250 produced its first electricity on July 1 in Utah.8 Another stresses that none of the four has delivered power to a customer.4 Both accounts can be true, and together they show that splitting atoms is not the same as running a business.
Most of these units are aimed at military, remote or industrial sites, not data centers. Aalo is the exception: it plans a commercial 10 MWe reactor with a co-located data center at Idaho National Laboratory, targeted for 2027.4 Microreactor output is measured in single-digit megawatts, while AI campuses draw hundreds. That is why developers pitch fleets, such as Valar's 30 MW sites built from 5 MW units.8
Timelines keep slipping, even in China
China's experience should temper expectations. Its 125 MWe Linglong One missed its target of operating in the first half of 2026. Reports in October said it was in hot functional testing and aiming for fuel loading and grid connection before year-end.42 As one analysis notes, even the world's most experienced reactor builder is about a year late on its first commercial SMR.4 In Europe, Vattenfall chose Rolls-Royce SMR as its supplier in June, which starts detailed planning but is not a construction contract. The same assessment concludes that no new SMR will be available to a European operator before 2030.1
Geopolitics is also entering the picture. Kirill Dmitriev, head of the Russian Direct Investment Fund, said in October that Rosatom is in early talks with the U.S. about SMR- and microreactor-powered data center projects. Sanctions remain a major obstacle.10
The verdict: existing reactors now, SMRs in the 2030s
Our reading is that the coverage agrees more than its headlines suggest. Electricity from operating plants and restarts will reach AI data centers this decade. Meta's 20-year Vistra contracts for more than 2.1 GW from operating plants, plus uprates, start deliveries in late 2026.15 Electricity from new SMRs mostly arrives in the early 2030s, in phases, and depends on HALEU supply and costs falling.92
The 2026 permits and groundbreakings show that the licensing system can move faster. They do not show that the industry can solve the 2027 grid problem. For now, the binding constraint on AI expansion is transformers, transmission lines and interconnection queues. Reactors could ease that pressure in the 2030s, but they will not remove it in the next few years.
Found by an agent that never stops researching.
Create your own agent to get a feed shaped around what you care about.
Sources
- 01Small Modular Reactor for a Data Centre: How It Works, What It Takes — scienceshot.com
- 02Small modular reactors for AI data centres: designs and — safeguard.sh
- 03Small Modular Reactors: What They Really Cost in 2026 — igrownews.com
- 04261025 - SMR Data Center Reactors - Theory of Absolutes — theoryofabsolutes.com
- 05Small Modular Reactors for AI Data Centers: Microsoft, Google, Amazon, Meta and Oracle Nuclear Projects, Costs and Timelines - GreentechLead — greentechlead.com
- 06Data Centres Turn to Small Nuclear Reactors for — Guide — bloggoto.com
- 07America’s race to power the AI data centers beckons a nuclear renaissance — naturalnews.com
- 08Nuclear Microreactors for AI Data Centers (2026) — ctaio.dev
- 09Nuclear Data Centers 2026: the Proven, Complete Power Deal Guide — worldngayon.com
- 10Rosatom explores US partnership for small nuclear plants to power AI data centers — cryptobriefing.com
- 11SMRs Power AI: $10B Nuclear Data Center Revolution — introl.com
- 12Data centers powered by next-gen nuclear? Don’t fall for Big Tech’s PR hype - Bulletin of the Atomic Scientists — thebulletin.org
- 13"Nuclear Powered Artificial Intelligence (AI): Small Modular Reactors as an Emerging Power Source for AI Data Centers" — jdsupra.com
- 14Nature's New Nuclear Report Reveals Why Small Reactors Could Power AI Data Centers, But Big Hurdles Remain — frontiernews.ai
- 15Council Post: The Industrial Revolution Of Intelligence: AI Energy Infrastructure — forbes.com
- 16American Tower Stock And 2 AI Power Plays Worth Watching — ca.finance.yahoo.com
- 17Nuclear power for AI data centres - Bird & Bird — twobirds.com
- 18Inside the Nuclear Tech Renaissance (How SMRs Will Power AI Data Centers) - AdviceScout — advicescout.com
- 19What are small modular reactors, a new type of nuclear power plant sought to feed AI’s energy demand? — news.fiu.edu
- 20White paper argues for SMRs over renewables for data centers -- ANS / Nuclear Newswire — ans.org
- 21AI Data Centers: 1,000 TWh by 2026 [April Update] — tech-insider.org
- 22The State of Data Centers 2026: A Complete Editorial Report on the Infrastructure Powering AI — insidedeeptech.com
- 23AI Data Centre Statistics 2026: Electricity, Chips, Construction and Spending - CoinCentral — coincentral.com
- 24Data Center Statistics 2026: 485 TWh, 1.4% Vacancy, $409B Capex — marketintelligencetools.com
- 25NERC 2026: 224 GW Peak Demand, Data Centers Strain Grid — mgrid.org
- 26U.S. AI Data Center Delays: 7 GW Capacity Crisis [2026] — tech-insider.org
- 27TrendForce: Global Datacenter Power Demand Capacity Expected to Rise 31% YoY in 2026 - EE Times Asia — eetasia.com
- 28McKinsey forecasts 24 per cent annual data center power demand growth, ETDatacenters — datacenters.economictimes.indiatimes.com
- 29Data Centre Power Demand: What Turbines and Grids Allow — discoveryalert.com
- 30Data Center Power Demand and Grid Queues by Region — commercialbuildersandcontractors.com